Baylor University

​

McLane Student Life Center Natatorium Refresh

In April 2020, Baylor approached the Office Of Moran Architects about designing improvements to the natatorium. They had a problem that many universities share: a big need but little funding.  

 

The goal was to create a menu of improvements that could be made over
time with the first improvements being during the 2020  summer. The final plan includes:

 

  • Plantings and container designs.

  • New perimeter LED lighting that can be re-lamped from the pool deck.

  • Banners that can add large scale color, branding and are easily replaced.

  • Fan specifications for use to improve the ventilation. 

  • Budgets for the above & confirmation of immediate materials availability. 

  • Concepts for additional improvements.

 

Phase 1 of this project is underway and will be installed before students arrive back in Fall, 2020. 